(Solved)3. Given the project network and baseline information below
3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8?
2 B 8 8 D 12
0 A 2 0 0 0 0 12 F 15 LEGEND
0 0 2 6 8 8 4 12 0 0 ES ID EF
2 2 2 12 3 15 SL SL
2 C 7 7 E 10 LS DUR LF
2 2 2 2
4 5 9 9 3 12
End of Period 4
Task Actual % Complete EV AC PV CV SV
A Finished —— 300 400 —— ——
B 50% —— 1000 800 —— ——
C 33% —— 500 600 —— ——
D 0% —— 0 —— —— ——
E 0% —— —— —— —— ——
Cumulative Totals —— —— —— —— ——
End of Period 8
Task Actual % Complete EV AC PV CV SV
A Finished —— 300 400 —— ——
B Finished —— 2200 2400 —— ——
C Finished —— 1500 1500 —— ——
D 25% —— 300 0 —— ——
E 33% —— 300 —— —— ——
F 0% —— 0 —— —— ——
Cumulative Totals —— —— —— —— ——