Assuming a 24 hour operation in a warehouse, and an arrival following Poisson distribution with mean rate of 36 per day and service (unloading using a single bay) following exponential distribution with a rate of 48 trucks per day, answer the following question. What is the expected waiting time in the system (in hours) for a typical truck?
2 hours
1 hour
1.5 hour
0.25 hour
0.5 hours
Expert Answer
Answer to Assuming a 24 hour operation in a warehouse, and an arriv. . .