(Solved)Capacity Planning Exercises 1. For the information below, d
Capacity Planning Exercises 1. For the information below, develop rough cut capacity plan (RCCP) for the MPS using: (1) a rough cut using routings (capacity bills method, and (2) a resource profile method (offsetting by lead time) WEEK WEEK 200 WORK CENTER SETUP HOURS RUN HOURSAUIT LEAD TIME 201 302 Part X Part Y Part Z Part R 1 week 1 week 10 400 500 12 1.0 2 week) i week i week)
https://d2vlcm61l7u1fs.cloudfront.net/media%2F292%2F292a97e9-5156-4765-9ec9-5e7acd1a1604%2FphpIlVdHD.png
Expert Answer
Answer to Capacity Planning Exercises 1. For the information below, d. . .
OR